Sparrow Clinton Hospital’s new Emergency Services Department progressing as expected

Sparrow Clinton Hospital’s Emergency Services Department construction project is progressing as expected. All foundations are completed and the new facility site has been connected with the existing sanitary sewer. Underground plumbing and electrical work is underway. By mid-November, Granger will begin pouring the concrete floors and installing the steel framework.

column supports  Support structure  laying pipe

In these photos, note the large “boxes” that mark the locations for installation of the structural steel support columns.